12th Feb 2010 -
The N18 Oranmore to Gort Scheme has been combined with the M17 Galway to Tuam Scheme and the N17 Tuam Bypass scheme into one large scheme 57 kilometres long, known as the N17 N18 Gort Tuam PPP scheme. This scheme will be progressed as a PPP scheme, whereby the scheme will be constructed and maintained with mostly private finance . The scheme is currently out to tender and it is anticipated that a contract to commence construction of the scheme will be awarded at the end of 2010.
The tendering process for the N17 N18 Gort Tuam PPP scheme is being managed by the National Roads Authority. The scheme will be constructed as a four lane road. There will be no tolls on the road. Further details on the scheme can be found on the NRA website at the following link
http://www.nra.ie/PublicPrivatePartnership/SecondPPPRoadsProgramme/
M17 News March 2009
Copy of correspondence from An Bord Pleanála confirming Compulsory Purchase Order for M17 Galway to Tuam
Copy of correspondence from An Bord Pleanála confirming M17 Galway to Tuam EIS
14th April 2008 - An Bord Pleanála have advised that the Oral Hearing for the M17 Galway (Rathmorrissy) to Tuam Scheme will be held in the Marriot Hotel, Headford Rd. , Galway on Wednesday 23rd April 2008 at 11:00am. The Inspector is Mr. Billy Moore. 143 CPO and 102 EIS submissions have been made.
The following documents will be available for viewing during the Oral Hearing:
- Constraints Study Report and Route Options (June2000)
- Constraints Study Addendum Report and Route Options (December 2001)
- Route Selection Report and Cost Estimate (August 2003)
- Supplementary Route Selection Report (June 2006)
- EIS (November 2007)
- MO (November 2007)
- N17 Galway to Tuam Preliminary Site Investigation, Factual Report (Oct 2002)
- N17 Galway to Tuam, Co. Galway , Factual Report on Site Investigation (Sept 2006)
- Geotechnical Interpretative Report, (October 2006)
- Factual Report on Infiltration Tests N17 Galway to Tuam, Mouchel Parkman (July 2007)
- Winter Bird Survey for Galway - Tuam Proposed N17 Route , (March/April 2007)
Published since EIS published
- Bat Fauna Studies 2002-2007 Addendum Report, (Feb 2008)
- M17 Galway (Rathmorissy) to Tuam Additional Boreholes, Site Investigation Factual Report (March 2008)
See short report on archaeological discoveries on this project
PDF of Schedule (File Size 1.1Mb)