Welcome

This site provides information on the N18 Gort to Crusheen Dual Carriageway scheme. The project is being promoted by Galway County Council. For the section within County Clare, the scheme is being undertaken by Galway County Council on behalf of Clare County Council in accordance with agreements made under Section 85 of the Local Government Act, 2001 and approved by the National Roads Authority under Section 14(8) of the Roads Act, 1993.

Project Schedule

First Public Consultation & Constraints Study March 2000
completed
Second Public Consultation & Emerging Preferred Route
June 2000
completed
Route Selection Report December 2000
completed
Publish Compulsory Purchase Order (CPO) February 2006
completed
Publish Environmental Impact Statement (EIS)
February 2006
completed
Oral Hearing

25th July 2006
completed

Scheme approved by An Bord Pleanala August 2007
Tenders returned April 2008
Contract awarded to SIAC Wills JV Ltd. October 2008
Projected completion date Summer 2011