This site provides information on the N18 Gort to Crusheen Dual Carriageway scheme. The project is being promoted by Galway County Council. For the section within County Clare, the scheme is being undertaken by Galway County Council on behalf of Clare County Council in accordance with agreements made under Section 85 of the Local Government Act, 2001 and approved by the National Roads Authority under Section 14(8) of the Roads Act, 1993.
| First Public Consultation & Constraints Study | March 2000 completed |
| Second Public Consultation & Emerging Preferred Route |
June 2000
completed |
| Route Selection Report | December 2000 completed |
| Publish Compulsory Purchase Order (CPO) | February
2006 completed |
| Publish Environmental Impact Statement (EIS) |
February 2006
completed |
| Oral Hearing | 25th July 2006 |
| Scheme approved by An Bord Pleanala | August 2007 |
| Tenders returned | April 2008 |
| Contract awarded to SIAC Wills JV Ltd. | October 2008 |
| Projected completion date | Summer 2011 |